30/06/24 | 6:42 pm

Print

Delhi metro to open its phase 4 priority corridors by 2026, over 50 per cent work already done

The Delhi Metro Rail Corporation (DMRC) announced on Sunday that it is rapidly advancing with its Phase 4 expansion, aiming to open all three priority corridors comprising 65 kilometers of new lines by 2026.

In a post on X, DMRC said that over 50 percent of the work on these corridors has been completed. Specifically, the Majlis Park-Maujpur section has reached about 80 percent completion in civil work. Tunneling is ongoing on the Aerocity-Tughlakabad (Golden Line) and Janakpuri West-RK Ashram Marg (Magenta Line) corridors.

Regarding delays in the project, DMRC explained that despite beginning Phase 4 in December 2019, the project faced significant delays from 2020 to 2022 due to the COVID-19 pandemic and challenges in obtaining tree-cutting permissions. The DMRC noted that substantial work on the project has been ongoing for the last one and a half to two years, aiming for completion by 2026.

The section from Janakpuri West to Krishna Park Extension is nearly finished and is expected to open by August 2024, with the Majlis Park-Maujpur corridor also slated for completion next year. Other sections will open gradually by 2026.

However, the DMRC is still awaiting certain permissions related to tree-cutting and land acquisition at specific sites. High-level site visits are being conducted to expedite the work, and the necessary tree-cutting approvals are actively being pursued.

Additionally, two new corridors, Inderlok-Indraprastha and Saket G Block-Lajpat Nagar, have recently received approval.

“The project is being monitored at various levels on a day-to-day basis. Site visits are also taken up at the highest level to expedite the work. Tree-cutting permissions are being pursued at appropriate levels,” said DMRC in an official statement.

The DMRC is currently securing statutory clearances, including land acquisition, and is in the process of planning and tendering for further civil works, ensuring the project remains on track for its 2026 completion target.

RELATED ARTICLES

2 hours ago | Har Ghar Tiranga movement

PM Modi urges people to join Har Ghar Tiranga movement, hoist Tricolour at homes

Prime Minister Narendra Modi on Sunday urged citizens to participate enthusiastically in the Har Ghar Tiranga movement and renew their collective resolve to contribute towards building a Viksit Bharat. Sharing Ministry of Culture's post on X, PM Mod...

2 hours ago | Base Hospital

Operation Sindoor showed India will go to any extent to protect its citizens: Rajnath Singh

Defence Minister Rajnath Singh on Sunday said Operation Sindoor sent a clear message to the world that India would go to any extent to ensure the safety of its citizens while protecting the dignity symbolised by the sindoor worn by women. Addressing...

3 hours ago | 'Har Ghar Tiranga' Abhiyan

Vice President Radhakrishnan launches Har Ghar Tiranga Abhiyan in Andaman & Nicobar Islands

Vice President C. P. Radhakrishnan on Sunday launched the ‘Har Ghar Tiranga Abhiyan’ in the Andaman and Nicobar Islands by hoisting the National Flag at Flag Point in Sri Vijaya Puram on the occasion of August Kranti Diwas, commemorating the Quit...

30/06/24 | 6:29 pm

Print

Delhi metro to open its phase 4 priority corridors by 2026, over 50 per cent work already done

The Delhi Metro Rail Corporation (DMRC) announced on Sunday that it is rapidly advancing with its Phase 4 expansion, aiming to open all three priority corridors comprising 65 kilometers of new lines by 2026.

In a post on X, DMRC said that over 50 percent of the work on these corridors has been completed. Specifically, the Majlis Park-Maujpur section has reached about 80 percent completion in civil work. Tunneling is ongoing on the Aerocity-Tughlakabad (Golden Line) and Janakpuri West-RK Ashram Marg (Magenta Line) corridors.

Regarding delays in the project, DMRC explained that despite beginning Phase 4 in December 2019, the project faced significant delays from 2020 to 2022 due to the COVID-19 pandemic and challenges in obtaining tree-cutting permissions. The DMRC noted that substantial work on the project has been ongoing for the last one and a half to two years, aiming for completion by 2026.

The section from Janakpuri West to Krishna Park Extension is nearly finished and is expected to open by August 2024, with the Majlis Park-Maujpur corridor also slated for completion next year. Other sections will open gradually by 2026.

However, the DMRC is still awaiting certain permissions related to tree-cutting and land acquisition at specific sites. High-level site visits are being conducted to expedite the work, and the necessary tree-cutting approvals are actively being pursued.

Additionally, two new corridors, Inderlok-Indraprastha and Saket G Block-Lajpat Nagar, have recently received approval.

“The project is being monitored at various levels on a day-to-day basis. Site visits are also taken up at the highest level to expedite the work. Tree-cutting permissions are being pursued at appropriate levels,” said DMRC in an official statement.

The DMRC is currently securing statutory clearances, including land acquisition, and is in the process of planning and tendering for further civil works, ensuring the project remains on track for its 2026 completion target.

RELATED ARTICLES

3 hours ago | digital procurement platform

Where every purchase finds a GeM: How India’s digital procurement platform is reshaping government buying

Ten years after its launch, the Government e-Marketplace (GeM) has evolved from a digital procurement platform into a major pillar of India’s public procurement ecosystem, bringing government buyers and sellers onto a common, technology-driven mark...

4 hours ago | MDR

UPI to remain free for users; nominal MDR may apply to limited merchant transactions

The Centre on Saturday clarified that users will not be charged for making payments through the Unified Payments Interface (UPI), amid concerns over the recent amendment to the Payment and Settlement Systems Act (PSS Act). The government said all Pe...

12 hours ago | AMIT SHAH

Amit Shah launches ‘Bank in a Box’, Security Operations Centre for Urban Cooperative Banks

Union Home Minister and Minister of Cooperation Amit Shah on Saturday inaugurated the new premises of the National Urban Cooperative Finance and Development Corporation (NUCFDC) in Mumbai and launched a series of technology and cybersecurity initiati...